Flying weighing

With the "flying" aggregate dosing and weighing system a dosing accuracy of down to 2 kg can be achieved

With the "flying" aggregate dosing and weighing system a dosing accuracy of down to 2 kg can be achieved

The ”flying” aggregate dosing and weighing system leads to remarkable savings in investment and even more importantly, reduced operational costs. Dosing is done by belt feeders with frequency controlled speed. With this system a dosing accuracy of down to 2 kg and a very low deviation in weighing can be achieved. At the same time reliably functioning aggregate moisture measuring allows to calculate the correct amount of water to be dosed into the water scale. The “flying” system can lead to cement savings of up to 30 kg/m3concrete (50 lbs/cubic yard).

Down to 2 kg (4 lb.) aggregate dosing precision can be achieved

Possibility to save of up to 30 kg cement per m3

Short weighing time increases the production capacity of the plant


 Makes possible 2-3 m (6-9 ft) lower aggregate bin filling level than usual

Makes possible 2-3 m (6-9 ft) lower aggregate bin filling level than usual

Dynamic ”flying” weighing moves aggregate during the process to holding hopper and thanks to that, aggregate conveyor needs very limited space. Aggregate bin construction can be made 2-3 m (6-9 ft) lower than normal weighing belt solution. Moreover filling level of the aggregate bin and filling ramp can be lowered 2-3 m, this saves space at the site. Lower filling ramp generates remarkable savings in fuel and operating costs of wheel loader.

2-3 m (6-9 ft) lower aggregate bin filling level

Lower filling ramp saves space at the site

Remarkable savings in fuel and operating costs of wheel loader


With the "flying" aggregate dosing and weighing system a dosing accuracy of down to 2 kg can be achieved The ”flying” aggregate dosing and weighing system leads to remarkable savings in investment and even more importantly, reduced operational costs. Dosing is done by belt feeders with frequency controlled speed. With this system a dosing accuracy of down to 2 kg and a very low deviation in weighing can be achieved. At the same time reliably functioning aggregate moisture measuring allows to calculate the correct amount of water to be dosed into the water scale. The “flying” system can lead to cement savings of up to 30 kg/m3 concrete (50 lbs/cubic yard).  Down to 2 kg (4 lb.) aggregate dosing precision can be achieved  Possibility to save of up to 30 kg cement per m3  Short weighing time increases the production capacity of the plant   Makes possible 2-3 m (6-9 ft) lower aggregate bin filling level than usual Dynamic ”flying” weighing moves aggregate during the process to holding hopper and thanks to that, aggregate conveyor needs very limited space. Aggregate bin construction can be made 2-3 m (6-9 ft) lower than normal weighing belt solution. Moreover filling level of the aggregate bin and filling ramp can be lowered 2-3 m, this saves space at the site. Lower filling ramp generates remarkable savings in fuel and operating costs of wheel loader.  2-3 m (6-9 ft) lower aggregate bin filling level  Lower filling ramp saves space at the site  Remarkable savings in fuel and operating costs of wheel loader   Allows simple and low-cost foundation also in mobile solutions

Allows simple and low-cost foundation also in mobile solutions

Thanks to the “flying” aggregate weighing system and low profile aggregate bin foundation is very easy to make. There is not needed underground constructions, only simple flat concrete slab is enough in stationary installation.

In mobile set-up plant is equipped with mobile steel foundation and aggregate bin filling ramp elements. It guarantees a rapid and cost-effective relocation and start-up of production.

Very easy foundation, flat concrete slab is enough in stationary installation

Mobile steel foundation for mobile set-up

Filling ramp elements for bins together with plant


5 reasons to purchase a portable concrete batching plant with the “flying” aggregate dosing and weighing system